Shop Floor Control - Batch Reschedule Work Orders

Function

When making changes to shop floor calendars or to the queue timeClosed A record of the average amount of time material will wait in line for the next operation. in Operation Code Maintenance, work orders that use the operation require rescheduling. Use this task to reschedule all work orders or a range of work orders, or just work orders of a certain type or priority, all at once. When the rescheduling is completed a report is created to show the changes made to the work orders.

To access this task...

Select Batch Reschedule Work Orders from the Inquiry and Maintenance menu.

Batch Rescheduling of Work Orders

About the Fields

In the Beginning/Ending Work Order No field...

In the Priority Code field...

  • Enter the lowest priority number to reschedule.

Checkboxes...

  • Mark the Open? box to reschedule open work orders.

  • Mark the Closed? box to reschedule planned work orders.

  • Mark the Planned? box to reschedule quoted work orders.

  • Enter any combination of the above.

When finished making entries to the fields...

  • Click run process button to complete the batch reschedule process.

  • Click save button to save the changes.

  • Click new/clear form button to clear the form and begin again.