Description
|
Formula
|
Estimated Yield
|
Production Quantity times Yield % equals Yield
Production Quantity Desired divided by Yield % equals Quantity Required on Production Order
|
Net Hours per Piece
|
(Hrs/Piece divided by Pieces/Hr) divided by Yield % plus (Setup Time divided by Standard Lot Size)
|
Direct Cost per Piece
|
Net Hours times Direct Rate
|
Overhead Cost per Piece
|
Direct Cost per Piece times Overhead Factor
|
Total Labor Cost per Piece
|
(Net Hours times Direct Rate) plus (Net Hours times Direct Rate times Overhead Factor)
-or-
Direct Cost plus Overhead Cost
|
Scrap Factor
|
Dimensions of Desired Piece divided by Dimensions of Original Piece, converted to %
|
Description
|
Formula
|
Net Quantity per Piece Material
|
Quantity Required times Alternate Factor divided by (Divisor times (100 - Scrap Factor)) divided by Yield %
|
Material Cost per Piece
|
Net Quantity times Unit Cost
|
Net Quantity per Piece Subcontractor
|
Quantity Required times Alternate Factor divided by Divisor
|
Subcontract Cost per Piece
|
Net Quantity times Unit Cost
|
Total Cost per Piece
|
Total Labor Cost plus Total Material Cost plus Total Subcontract Cost
|
Direct Cost per Production Quantity
|
Production Quantity times (Hours per piece times Direct Rate divided by Pieces per Hour) divided by Yield % plus (Setup Time times Direct Rate)
|
Overhead Cost per Production Quantity
|
Direct Cost per Production Quantity times Overhead Factor
|